YEAR

2006-2009

LOCATION

Space Coast, FL

ABOUT

JP. Donovan Construction, Inc. served as the prime contractor for six task orders for this multi-phase, multi-year project. The Eastern Processing Facility (EPF) Complex is over 40 acres with multiple facilities supporting the spacecraft processing facility main building.

  • Site preparation, roadways and parking
  • Steel fabrication and welding
  • Survivability, security (SCIF), cleanroom, floor space, door opening, interface requirements
  • Blast panels (DOD Explosive Safety Board), RF Shielding, and hypergolic compatibility requirements
  • Regional needs of the facility included 155 mph sustained hurricane wind survivability, 14 feet above sea level to survive storm surge, and security systems.